× Notice: This website or its third-party tools use cookies, which are necessary to its functioning and required to achieve the purposes illustrated in the cookie policy. If you want to know more or withdraw your consent to all or some of the cookies, please refer to the cookie policy. By closing this banner, scrolling this page, clicking a link or continuing to browse otherwise, you agree to the use of cookies.
×
Serving our customers through changing times.

Discover our new online meeting tool

Schedule a one on one virtual planning session with a professional civil engineer.

Connect With an Engineer

BOSS 2000 Storm Sewer Pipe Replacement

Owner: Town of Stettler
Engineer: Associated Engineering Alberta Ltd.
Contractor: Wooden Construction Ltd.
Location: Stettler, AB

As part of a sanitary main replacement project, the Town of Stettler, AB was faced with the challenge of replacing an aging storm sewer line under very low cover conditions.

After considering several options, Associated Engineering specified 750mm diameter BOSS 2000 HDPE storm pipe at 320kPa stiffness, complete with bell and gasket joints. The pipe was manufactured to surpass the requirements of CSA B182.8-02 for Profile Polyethylene Storm Sewer Pipe.

The design and construction of BOSS 2000 storm pipe offers a distinct weight advantage over conventional sewer pipe. The low weight of the BOSS 2000 pipe provides ease of handling, positioning, and installation that traditional pipe cannot match. The 750mm-diameter BOSS 2000 pipe on this project weighed only 30kgs/m, less than 1/10th the weight of conventional concrete pipe.

The robust character and durability of BOSS 2000 was put to the test when the contractor discovered an unmarked utility line. Forty-two meters of pipe had to be removed and reinstalled at a new grade. This was done with little effort and each section was reused with no loss of pipe due to damage!

Fewer joints, ease of installation, smaller equipment, and lower transportation costs all result in lower installed cost of pipe and savings to the town.

Armtec is proud of our diverse line of stormwater solutions and continues the tradition of offering innovative solutions at the best value to our customers.

BOSS 2000 was put to the test when the contractor discovered an unmarked utility line. Forty-two metres of pipe had to be removed and reinstalled at a new grade.

Not what you are looking for?